1, construction workers and welders should wear clean white fine gauze gloves (non-wearing cotton gloves).
2, the weld area treated and non-contact touch iron items.
3, welding work as much as possible in titanium bar supplier the room, the ambient wind speed should ≤0.5m / s, avoid the drafts affected.
4, welding wire when titanium welding with short arc welding, the use of small heat input welding, the welding nozzle and the holding angle of 70 to 80 degrees.
5, taking over the position welding,grade 3 titanium butt gap is generally about 0.5mm.
6, each weld should be possible once finished welding, seam welding must be connected before the weld interface should be clean, weld meat lap length is 10 ~ 15mm.
7, when the welding torch should not swing around, wire melting end not out of gas reserves.
8, ahead of the welding arc when aspirated, not lifted immediately when the torch extinction, should be delayed gas, until the temperature drops below 250 ℃.
9, a gas mask and protective distance drag the torch should be the shortest better,Titanium tube supplier seek contact with the wall of the smallest gap. When the tube butt welding, forming side welding in order to achieve the requirements of the welding carried out twice: once for the back cover welding (welding when you can not back fill material), and another for forming welding. When the multi-layer welding, must wait before a weld completely cooled, then the next weld bead.